As a user, I can see a warning when there are Tests in a Test Execution not associated with the Test Plan

    XporterXMLWordPrintable

Details

    • Story
    • Status: Closed
    • Major
    • Resolution: Fixed
    • None
    • R2.0.0
    • Core, User Interface
    • None
    • R2.0.0 S6
    • OK

    Description

      A warning should be visible on the Test Execution screen, when the Test Execution is linked with a Test Plan, and this Test Execution contains Test issues that are not in the Test Plan.

      In this case, the warning message must contain a button that will allow to associated all loose Tests with the Test Plan automatically.

      In case the Test Execution is associated with multiple Test Plans, then the warning must appear for each Test Plan issue.

      Attachments

        Activity

          People

            pmmr Pedro Rodrigues
            bmpc Bruno Conde
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved:

              Time Tracking

                Estimated:
                Original Estimate - 2 days
                2d
                Remaining:
                Remaining Estimate - 2 days
                2d
                Logged:
                Time Spent - Not Specified
                Not Specified